15 Jan 2018

Important Note's Related to SAP HANA


Supported Operating System for SAP HANA:
Before the SAP HANA installation can be started, you must configure the Linux system according to the recommended OS settings for SUSE Linux Enterprise Server (SLES) and Red Hat Enterprise Linux (RHEL). 
Note's: 
See SAP Note 2235581 - "SAP HANA: Supported Operating Systems" for an overview of all of the supported Linux versions. 

SUSE Linux Enterprise Server (SLES) for SAP 11 SP2. See SAP Note 1310037 and 1824819 - SAP HANA DB: Recommended OS settings for SLES 11 SP2 
SUSE Linux Enterprise Server (SLES) for SAP 11 SP3. See SAP Note 1310037 and 1954788 - SAP HANA DB: Recommended OS settings for SLES 11 SP3 
SUSE Linux Enterprise Server (SLES) for SAP 11 SP4. See SAP Note 1310037 and 2240716 - SAP HANA DB: Recommended OS settings for SLES 11 SP4 
SUSE Linux Enterprise Server (SLES) for SAP 12. See SAP Note 2205917 - SAP HANA DB: Recommended OS settings for SLES for SAP Applications 12 
Red Hat Enterprise Linux (RHEL) 6.6 for SAP HANA. See SAP Note 2013638 - SAP HANA DB: Recommended OS settings for RHEL 6.5 
Red Hat Enterprise Linux (RHEL) 6.5 for SAP HANA. See SAP Note 2136965 - SAP HANA DB: Recommended OS settings for RHEL 6.6 
Red Hat Enterprise Linux (RHEL) 6.7 for SAP HANA. See SAP Note 2247020 - SAP HANA DB: Recommended OS settings for RHEL 6.7 

See SAP Note 2188482 - SAP HANA on IBM Power Systems: Allowed Hardware 

Note Related to Multiple SAP HANA SID's on one SAP HANA System: 
As of SAP HANA SPS09, SAP supports running multiple SAP HANA systems on a single host In production. This is restricted to single host and scale-up scenarios only. Keep in mind that multi-SID requires significant attention to various detailed tasks related to system administration and performance management. For more information:
 read SAP Note 1681092 - Multiple SAP HANA DBMS's (SID's) on one SAP HANA System.

The SAP HANA hardware directory can be found at: 
https://www.sap.com/dmc/exp/2014-09-02-hana-hardware/enEN/index_html. 

1 Jan 2018

SAP HANA Course and Certification codes

HANA Books & Course Details:

HA100 - SAP HANA Introduction
HA200 - SAP HANA Installation & Administration
HA215 - SAP HANA Monitoring and Performance tuning
HA240 - Authorisation, Security and Scenarios
HA250 - Migration to SAP HANA using DMO
HA350 - SAP HANA Data Provisioning
HA355 - SAP HANA Smart Data Integration
HA500 - SAP HANA Vora
BW305H, BW310H and BW362 - SAP BW on SAP HANA

Latest HANA Administration Certification is:
C_HANATEC_13 - SAP Certified Technology Associate - SAP HANA 2.0

S/4 HANA Conversion Certification:
E_S4HCON_75 - SAP Certified Technology Specialist - SAP S/4HANA Conversion and SAP System Upgrade

6 Feb 2017

SAP Solution Manager 7.2 Updates

Dear Consultants,
Below are the few new points in Solution Manager 7.2 Compare to 7.1
1. SolMan 7.2 will not support dual stack, it is now individual ABAP & JAVA stacks.
2. We need to install Both the instances Separately.
3. The SID of Both the instances is different.
4. Java will not have any UME, so while installing JAVA stack we need to provide the UME as SolMan ABAP.
5. J2ee_Admin & J2ee_Guest will be created while installing ABAP Stack in ABAP system.
6. SLD resided in JAVA stack.
7. SMSY transaction no more in 7.2. it will be routed to LMDB.
8. SOLMAN_SETUP is having new tabs for configuration
9. SOLMAN_WORKCENTER required Fiori setup. Content and tabs in this T-CODE have been changed as Fiori Tiles.
10. SOLAR_PROJECT_ADMIN will not work in 7.2
11. No Project Concept in 7.2
12. No Logical system assignments, new Logical grouping concept for Landscapes.

13. From Solution Manager 7.2 SP5 onwards, it is mandatory to use HANA DB or TREX to display process diagrams in Best Practice Packages.


Will be adding More.....

5 Feb 2017

Suite on HANA Sizing

Hi,

There are two way's to move to Suite on HANA Environment.
1. New Green Field Implementation.
2. Migration from Traditional database to HANA.

1. New Implementation:
For a New implementation, we will do Sizing using Quick Sizer Tool (HANA).
Link for quick Sizer: https://websmp102.sap-ag.de/sizing
Go to above link and select Quick Sizer HANA Version

2.Migration from the Traditional database to HANA.
For a Migration, we will do sizing using a report provided by SAP.
Sizing Suite on HANA: SAP NOTE: 1793345 & 1872170, 1514966
Sizing BW on HANA: SAP NOTE: 1637145

Sap Note 1872170 will have report, we need to apply this note in SAP system and need to run the report to estimate the sizing of Memory(RAM) and storage(Hard drive size).
Recommended to run this report when there is less users in the system. This report may cause performance issues if we run in business hours.